Hi Martin, 

I can't answer your last two questions, but the structure is Cross Laminated Timber panels  ( CLT ) and it is the Hot New Thing for commercial mid rise construction .The strength of concrete with just 16 % of the weight. 

First time I saw pictures,  my thought was " Egad, that's a lot of wood! " but I'm warming to it. 

I asked the closest rep, an engineer with StructurLam, what sort of shear a vertical panel of CLT is good for, and he told me their SLT3 panel ( 99 mm, or 3.2" thick ) can take up to 6000 lbs/lf.  

So now I'm looking at using CLT for the floor and bearing + shear elements of a current project of four little 2 story row houses in SB  in Oakland. Put up the kit, and then wrap it in bales. 

No, they're not paying me to shill for them. 

Bob
On May 15, 2013, at 9:27 AM, martin hammer wrote:

> Thanks Andre.  This is great.  I have a long-standing dream of a high-rise
> strawbale building (infilling a steel or concrete frame structure).  These
> mid-rise buildings are amazing to see.
> 
> Is the primary structure heavy timber post and beam?  Did someone from the
> French strawbale community act as a consultant for the straw bale aspects?
> Did the architect in the video have previous experience with straw bale
> building?
> 
> Martin
> 
> 
> On 5/15/13 5:05 AM, "contact at lamaisonenpaille.com"
> <contact at lamaisonenpaille.com> wrote:
> 
>> Here is a (french) article with a video on 2 recent 7story SB buildings
>> in France.
>> 
>> The Jules Ferry résidence, close to downtown St Dié in Les Vosges (88)
>> Acording to Passiv Haus standard (15 kWh/m2) this social housing should
>> exceed 130€ per year for heating, cooling, ventilation and warm water
>> costs for an appartment of 90m² (about 900ft²).
>> 
>> The size of the prefab panels have been optimised in order to facilitate
>> transport and installation. The project was cost-effective due to that
>> optimisation and the fact that the insulation (the prefab panels) also
>> carry the weight of the rainscreen. That way, an extra structural system
>> (for carrying the weight of the rainscreen so far appart from the
>> concrete structure) was avoided.
>> Total cost : 5 milion €
>> 
>> http://www.actu-environnement.com/ae/news/construction-immeuble-bois-paille-18
>> 315.php4 
>> 
>> 
>> Bale on,
>> André
>> _______________________________________________
>> GSBN mailing list
>> GSBN at sustainablesources.com
>> http://sustainablesources.com/mailman/listinfo.cgi/GSBN
> 
> 
> _______________________________________________
> GSBN mailing list
> GSBN at sustainablesources.com
> http://sustainablesources.com/mailman/listinfo.cgi/GSBN




More information about the GSBN mailing list